JEO / Constructors reported curb & gutter on B Street were replaced the week of October 30. Because of weather delays on other projects, Constructors has not been able to start on laying the asphalt on the interior roads. To maintain a quality project, they did not recommend doing the project this calendar year and have asked for an extension to April of 2018. After a lengthy discussion about liquidated damages, the current condition of the roads, interest rates, and the possibility of Nebco, a related company of Constructors purchasing the bonds, the matter was tabled until board could have a special meeting with all involved parties at later in the month to discuss the terms to modify the contracts. 